A plumber laying 500meters of drain pipe requires 20men working for 10days. What length in meters would be laid by 50men in 5days, if they all work at same rate?

Respuesta :

onyebuchinnaji
onyebuchinnaji onyebuchinnaji
  • 06-06-2020

Answer:

50men working in 5days will lay 100 meters

Step-by-step explanation:

If 20men working for 10days lays 500meters

then, 1 man will lay 10,000 meters in 10 days

also, 1 man will lay 1000 meters in 1 day

If 1 man lays 1000 meters in 1 day,

Then, 50 men will lay (1000 meters / 50 );  20 meters in 1 day

also, the same 50 men will lay (20 meters x 5days); 100 meters in 5 days.

Therefore, 50men working in 5days will lay 100 meters

Answer Link

Otras preguntas

a rectangle has an area of 30 square meters and a perimeter of 34 meters. what are the dimensions of the rectangle?
The volume of a rectangular prism is 270 cubic centimeters. The height of the prism is 5 centimeters. What should the length and width of the prism be? Explain
How many times dose 150 go into 1000
what are the next three numbers in this pattern 1,2,3,5,8
what british policy did american colonists protest at the boston tea party
find the value of x to the nearest whole number. Tan x(degree) = 1.732
what are the factor pairs of 38
Where and when did Martin Luther King Jr. die?
ray wants the larger of two aquariums.One aquarium has 20 in. by 20 in. and has a height of 18 inches.The other aquarium has a base that is 40 in. by 12in. and
Jim has a box in the shape of a rectangular prism. The area of the base of the box is 48 square inches. The volume of the box is 144 cubic inches. let h= the he