It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

What are at least 3 events that directly effected georgia's population in the years 1900-1950
Larry does not want to save his internet browsing details on his computer. what files should larry delete to clear his information from the computer?
What is the best definition for the underlined word based on the following sentence: "Many websites attempt to lure users in by promising them free access to pi
A bag contains 13 dark chocolates, 16 white chocolates, and 11 milk chocolates. Maggie’s class teacher, Jill, is very strict, and the probability that she offer
what is the difference of 81.035 and 9.76
How do I find the 25th term of the arithmetic sequence -39, -31, -23, -15,...
Which phrase correctly completes this conversation? Manuela: El restaurante La Hacienda es el mejor de la ciudad. Ricardo: Es verdad. Sirve _____
For the graph x=-3 find the slope of a line that is perpendicular to it
Find the slope and intercepts for each line.
Which term describes foods that have a high amount of nutrients relative to the number of calories they possess? A. portion control B. Food Guide Pyramid C.