Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Which of the following does not reflect the fourth step of effective communication? a. A student asks the teacher for clarification on the assignment. b. A wo
A qué equipo pertenece jesus Molina
Please help!! The Lion, The Witch, and The wardrobe questions - Why do the children slow down and allow themselves more rest time? Why do the children slow dow
What is the total number of carbon atoms in a molecule of ethanoic acid?(1) 1 (3) 3(2) 2 (4) 4
What best describes a grizzly bears habitat ?
Which is the best definition of a phylogenetic tree
Albert Einstein was originally from _____. Germany Italy France The United States
By 2002 more than 29 million people in sub-Saharan Africa lived with the virus that causes
Which statement best explains the relationship between the electric force between two charged objects and the distance between them? As the distance increases b
Line k has a slope of 2/3. If line m is parallel to line k, then it has a slope of -2/3 -3/2 2/3